Re: Target Date vs Baseline in Project Management Office template
Baseline dates are for capturing the dates that were determined at the beginning of a project. Planned / Target dates are for planning/adjusting tasks during the project. So if there's weather delays…1 · -
Re: Need a column to auto populate the month NAME when the date column next to it is selected.
Hi @sjohanson Here you go: =IF(MONTH([Final Completion Date]@row) = 1, "January", IF(MONTH([Final Completion Date]@row) = 2, "February", IF(MONTH([Final Completion Date]@row) = 3,…2 · -
Re: If Formula help
Hi @Kelly P. I just wanted to put this out there too. I copy and pasted your question into the AI create a formula feature just to see what it would do. The formula came out slightly different but wi…2 · -
Re: How do I remove just one person from receiving automated email reminders?
Hi @Taylor Berry The user can turn off the notifications themselves by clicking on their profile (lower left) and then choosing Notifications and unchecking what they don't want. I hope that helps. M…1 · -
Re: How to create a sheet with over 400 columns?
Hi @Derek Arnoldi Smartsheet provides a complete Project Management platform that can summarize data into a single sheet if you'd like. However managing work on that same sheet is not really how its …1 ·